300,000 TPA Copper Smelter plant at Konkola Copper Mines, Chingola Zambia

  • Client : Konkola Copper Mines, Chingola, Zambia
  • Process Licensor : Outotec
  • Consultant : Aker Kaverner
  • Scope :
  • Complete Mechanical Erection of smelter and allied equipments including piping, ducting and structurals.
  • Tanks and Vessels: 100 MT
  • Structural : 800 MT
  • Ducting: 500 MT
  • Piping: 120,000 Inch Meter
  • Equipments: 900 MT
  • Furnaces: 2100 MT
  • Castwheel: 70 MT

  • Year of Execution: 2008

Project Gallery

News

21 Feb, 2018

FURNACE FABRICA AWARDED CONTRACT FOR PHOSPHORIC ACID PLANT IN TAMIL NADU (INDIA)

Details: Design, Manufacture, Supply, Erection, Commissioning and Demonstration of Performance Guarantee of 800 TPD Phosphoric Acid Plant

27 Oct, 2017

FURNACE FABRICA AWARDED CONTRACT FOR PHOSPHORIC ACID STORAGE TANK IN TAMIL NADU (INDIA)

Details: Design, Engineering, Procurement, Construction and Erection of Phosphoric Acid Storage Tank (India)

11 Aug, 2017

FURNACE FABRICA AWARDED CONTRACT FOR COMPOSITE WORKS OF UTILITY AND OFF-SITE

Details: Composite works of Utility and Off site for revival of Fertilizer Complex in Telengana (India).

18 July, 2017

FURNACE FABRICA AWARDED CONTRACT FOR CONCENTRATED ACID PLANT PROJECT IN MOROCCO

Details: Supply and Installation of metallic pipes and equipments for acid plant project

12 April, 2017

FURNACE FABRICA AWARDED CONTRACT FOR CCR PROJECT

Details: Civil and Structural Works for CCR Project and LNG Relocation Works

27 Feb, 2017

FURNACE FABRICA AWARDED CONTRACT FOR REFINERY IN KOCHI

Details: Site enabling works for BS-VI MS Block Project